Princes Hwy – Jervis Bay Rd Int. Upgrade
PROJECT SUMMARY
LENGTH
2 kms
Civils
Overpass and Int Upgrades 
Road widening from 2 lanes to 4 lanes
		UTILITY TREATMENTS
MAIN WORKS
tbc
ENABLING WORKS
tbc
UTILITY AUTHORITIES
Endeavour Energy
Telstra
Optus
Shoalhaven Water
Council & RMS
KEY UTILITIES
Potable Water: 300/375mm diameter
Electrical: incl. 11kV 
Comms: multiple fibres
Drainage: Box Culverts
AT A GLANCE
Client: TfNSW
Project Value: tbc
AUS Start: Nov 2021
AUS Finish: Dec 2023
AUS Role: Utilities Coordination
AUS Team: PM
Works: 30 Treatments
AUS ROLE
AUS has been engaged by TfNSW as a Utilities Coordinator, embedded within the TfNSW team taksed with assisting the TA develop utility strategies, and undertake utility designs and obtain certifications.
We are required to review the design consultant’s utility designs for accuracy, completeness and readiness for construction in order to mitigate risks We are also required to assist the design consultant in managing the interface with the utility authorities to ensure that utility designs are delivered in alignment with the project milestones.
Description of Service Scope:
- Utilities Project Management & Coordination
 - Utility Clash Assessment Checks
 - Utility Constructability & Staging advice
 - Utilities review of the Designs (Contestable – Water & Electrical) & Treatment Plans, including assisting obtaining Scope of Works and Letters of Offer from the utility Authority
 - Checking Utility Tender Estimates and Utility Construction Programs
 - Interdisciplinary concept designs reviews 80, 100%
 - Utilities Transaction, Contract & Delivery advice
 - Subject Management Expert services for technical tender submissions review
 - Reviewing Utility Specifications for inclusion in Tender/Contract
 - 3rd Party Utility Agreement advice & Interface Management
 - Property acquisition and Easements planning & advice
 - Early/Enabling Works Advice
 
								