Newcastle Light Rail
PROJECT SUMMARY
LENGTH
2.7 kms
STATIONS
6 x stations
TRAMS
Urbos 100 x 33m
UTILITY TREATMENTS
MAIN WORKS
circa 130 Relocations
UTILITY AUTHORITIES
				Ausgrid  
Hunter Water 
Jemena 
Telstra, Optus, NBN, TPG 
Sydney Trains 
RMS & Council 					
						KEY UTILITIES
				Potable Water: 1200mm diameter 
Wastewater: 3000mm x 1220mm  
Gas: Jemena HP 1,050kPa  
Electrical: incl. 11kV High  Voltage OH & UG, Substations   
Comms: incl. 244 pair fibres					
						AT A GLANCE
Client:  Transport for NSW 
Project Value: $260m  
AUS Start: Dec 2015 
AUS Finish: Feb 2016
AUS Role: Utilities Management 
AUS Team: Utilities Lead + GIS
Works: 130 utility treatments  60
AUS ROLE
				AUS has overall responsibility for the management of utilities on behalf of TfNSW. Our commission started through procurement including Tender Negotiations/Contract Award and continued through Construction. Our Scope included pulling together the utilities scope (defined by others), the creation and management of a Utilities GIS, Constructability reviews and staging plans, preparation of Tender Estimates and Utilities Programs and claims advice and managing the Technical Advisor.  					
						Description of Service Scope:
- Utilities Project Management & Coordination
 - Utility Clash Assessment (Registers & Drawings)
 - Utility Digital Engineering GIS
 - Utility Constructability & Staging advice
 - Utilities Designs (Contestable – Water & Electrical) & Option Papers,
 - Obtaining Scope of Works and Letters of Offer for the utility Authority
 - Obtaining Utility Tender Estimates and Utility Construction Programs
 - Preparing and updating the Utilities Management Plan
 - Utilities Transaction, Contract & Delivery advice
 - Utility Specifications advice
 - 3rd Party Utility Agreement advice & Interface Management during Construction
 - Property acquisition and Easements planning & advice
 - Utilities Contract & Claims Management 
 
								

