Parramatta Light Rail – Stage 2

PROJECT SUMMARY

LENGTH
9 kms 
STATIONS
15 x stations 
TRAMS
tbc

UTILITY TREATMENTS

MAIN WORKS
tbc
ENABLING WORKS
tbc

UTILITY AUTHORITIES

Ausgrid
Endeavour Energy
Sydney Water
Jemena, Caltex, Viva
Telstra, Optus, NBN, TPG
Sydney Trains
RMS
Council

KEY UTILITIES

Potable Water: 2 x1200mm diameter
Wastewater: 1200mm diameter
Fuel: Viva 7,000kPa
Gas: Jemena 1,050kPa High Pressure
Electrical: incl. 33kV Transmission & Substations
Comms: incl. 720 pair fibres

AT A GLANCE

Client: Transport for NSW (TfNSW)
Project Value: TBC
AUS Start: Apr 2017
AUS Finish: Ongoing
AUS Role: Utilities Management
AUS Team: (3 x utility specialists) = Utilities Lead + 1 x Area PM’s + GIS   
Works: tbc

AUS ROLE

Description of Service Scope:

AUS has overall responsibility for the management of utilities on behalf of TfNSW for the preparation of the Final Business Case. Our Scope includes defining the utilities scope, undertaking utility concept designs, the creation and management of a Utilities GIS, Constructability reviews and staging plans, preparation of Tender Estimates and Utilities Programs.

  • Utilities Project Management & Coordination
  • Utility Clash Assessment (Registers & Drawings)
  • Utility Digital Engineering GIS’s & 12D
  • Preparing the Utilities Survey Scope (PS321)
  • Utility Constructability & Staging advice
  • Utilities Concept Designs
  • Peer Review of  Utility Tender Estimates
  • Preparing Utility Construction Programs 
  • Interdisciplinary designs reviews 
  • Preparing and updating the Utilities Management Plan
  • 3rd Party Utility Agreement advice
  • Property acquisition and Easements planning & advice
  • Early/Enabling Works Scoping